Thursday 5 December 2013

Stage 2 Tunnelling Progress

 S-604 is moving beneath with good speed and is now at 346 rings, past the halfway mark. It will bore beneath the road interchange at Farrer/Adam next and shall reach Botanic Gardens in due course, estimated around Feb 2014.
S-604(BP) below the Crown Centre bus stop (Botanics breakthrough point towards the left end)

S-603 at KAP has encountered terrible soil issues and the specialist have been engaged to do intensive soil improvement works to the area outside the Cascadia. As such the middle carriageway has been closed while they conduct the grouting.
S-603 (EP) encountering weak soil beneath the Cascadia

No comments:

Post a Comment

Note: only a member of this blog may post a comment.