Tuesday 4 November 2014

Watten Estate

The future entrance B of Tan Kah Kee station has begun to take shape along Dunearn Road. Spending the last 2 months on foundation works, piling and formwork for the staircase and lift shaft is completed. The project team progresses to work on the roof now as well as utility diversions and preliminary works on the foundation for the POB's intermediate column along the canal bank.



Add caption



No comments:

Post a Comment

Note: only a member of this blog may post a comment.